AI construction progress tracking means comparing site photos, 360 captures or laser scans with the BIM model and the programme, so the percentage complete for each area and activity is measured from evidence rather than estimated, and slippage on the critical path shows within the week.
Reality-capture platforms already turn a walk with a 360 camera into a navigable record, and some compare it with the model. The harder part is the link to the programme. Activities in Primavera P6 or MS Project are rarely broken down the same way as the model, so a wall recognised as built does not automatically move any activity forward. Without that mapping, progress tracking produces good pictures and the same Friday estimate.
So most of the build is the mapping: model elements and zones to programme activities, agreed with your planner, and then a weekly comparison that proposes progress per activity with the images that support it.